This week the municipal authorities decided that the new center will be built in Atucloma slaughter, Tarqui. Diego Caceres | Time
After a technical and financial analysis municipal authorities decided that the new center will be built in the slaughter Atucloma community, the Tarqui parish.
At the beginning of this administration he suspended the work citing problems topographic land owned by the Emurplag.
The decision was made this week and according to Santiago López, coordinator of municipal companies, were assessed aspects such as geographical location, the land was proper and livestock vocation of the area. Thus, according to the official, he had more evidence to make the final decision.
Another argument was that not all 36 hectares of land will be used for the new center slaughter, but only 6.6, which have an inclination of between 9 and 16 percent with a fully stable quality soil, according Lopez, guarantees any construction. All these elements were considered within the Land Use Plan February 2015.
Plan
The concept is handled for this project is a plant animal benefit, which also service despostaje a production area of cold cuts, plant meals and other services in order to make the most will be implemented to animal.
With this perspective execution is expected to cost about $ 20 million and financing would be through a public-private partnership, of which there are already some stakeholders but by far not released the names. Why it not defined when to proceed with the award and construction.
As a complement to the new center it was also decided that the new Fair livestock will be built in the Cumbe parish. The reasons weighed in this decision are the proximity to the future site and here already operates a similar fair, so you only need to make some adjustments.
Reaction
The president of the Vestry of Tarqui, Bolivar Saquipay said that after postponements construction, this resolution find it satisfactory, however stressed that their main concern is that the municipality complies with the compensation works such as road improvements, of sewerage and sanitation.
But also it expects the site to local labor is used, which would benefit economically Tarqui families.
On this Santiago Lopez he said that next week will meet with the authorities of Tarqui to discuss different topics to proceed with a plan requirements.
Background
The current camal of Cuenca, located in the area of Patamaraca, northeast of the city has more than 30 years of operation and according to authorities has served its useful life, so talk of new equipment needed.
The new land of 36 hectares was purchased in $ 76,000 during the last municipal administration. But in 2014, the current mayor, the purchase was questioned because allegedly had topographic problems.
The former manager of the Emurplag, Felipe Camacho, said at the time that the main problem was outstanding, "which make it impossible to build in this area". (JGJ) (I)
Source: http://www.eltiempo.com.ec/noticias-cuenca/188851-atucloma-ratificado-como-espacio-para-nuevo-camal/
0 comentarios: